You will see QTO has counted for Level 1: 4 Walls . Total linear takeoff - 100'.
You will see QTO has counted for
Level 2: 8 walls (4 on Level 1 and 4 on Level 2). Total linear takeoff of 170' instead of the correct 70.
Level 2: 8 walls (4 on Level 1 and 4 on Level 2). Total linear takeoff of 170' instead of the correct 70.
The good news is the Total Linear Takeoff for the PROJECT is correct. It is NOT Level 1: 100' + Level 2: 170'. It calculates the project total for Level 1:100' + Level 2:70'=170'.